Field Updatev

Installation of parts of the new athletic complex are set to begin soon, some as early as next week. Although initial plans were to start the process on Monday, July 24, officials say rain closer to Columbus had stalled the company, Maumee Bay Turf, on other projects. Practices are set to start Aug. 1 and all scrimmages have been moved to a different site. The process for installing new lights is also set to start next week, beginning with the concrete sleeves that serve as the foundation for the light poles. The scoreboard goes up the week of July 31.